This project is part of a partnership and financing agreement for the implementation of Drinking Water Supplyprojects for the centers and douars in the Rabat-Salé-Kénitra Region.

The works are carried out under the supervision of the Regional Agency for Project Implementation (AREP) in close coordination with local authorities.

The total budget allocated for this project is 6.3 million dirhams.

Partners

  • Ministry of Interior
  • Wilaya of the Rabat-Salé-Kénitra Region
  • Rabat-Salé-Kénitra Regional Council

Project Objectives

  • Strengthen drinking water supply in rural areas for the period 2022-2024.

Project Scope

Water SupplyComponent:

  • Connection to the existing ONEE BO network.

Distribution Component:

  • Installation of a distribution network over a 10.5 km line.
  • Construction of a semi-buriedreservoir with a capacity of 200 m³ and 40 m height to reinforce the existing network.